timmy-home/docs/lab-004-solar-deployment.md
Timmy fa450d8b19
Some checks failed
Smoke Test / smoke (pull_request) Failing after 20s
docs: LAB-004 solar deployment guide (#529)
Complete deployment guide for 600W cabin solar array:
- ASCII wiring diagram (panels → controller → batteries → inverter → AC)
- Parts list with estimated costs ($285-405, under $500 budget)
- 2S2P panel wiring configuration (36V to controller)
- 4-battery parallel bank layout
- Step-by-step installation checklist
- Safety notes and estimated runtime

Physical hardware task — documentation only.

Closes #529.
2026-04-15 21:45:16 -04:00

7.5 KiB
Raw Blame History

LAB-004: 600W Solar Array Deployment Guide

Issue #529 | Cabin Compute Lab Power System Budget: $200-500

System Overview

4x 150W panels → MPPT controller → 12V battery bank → 1000W inverter → 120V AC

[PANELS 4x150W]  ──series/parallel──►  [MPPT 30A]  ──►  [BATTERY BANK 4x12V]
                                                                  │
                                                           [1000W INVERTER]
                                                                  │
                                                        [120V AC OUTLETS]

Wiring Configuration

Panels: 2S2P (two in series, two strings in parallel)

  • Series pair: 18V + 18V = 36V at 8.3A
  • Parallel strings: 36V at 16.6A total
  • Total: ~600W at 36V DC

Battery bank: 4x 12V in parallel

  • Voltage: 12V (stays 12V)
  • Capacity: sum of all 4 batteries (e.g., 4x 100Ah = 400Ah)
  • Usable: ~200Ah (50% depth of discharge for longevity)

Parts List

Item Spec Est. Cost
MPPT Charge Controller 30A minimum, 12V/24V, 100V input $60-100
Pure Sine Wave Inverter 1000W continuous, 12V input $80-120
MC4 Connectors 4 pairs (Y-connectors for parallel) $15-20
10AWG PV Wire 50ft (panels to controller) $25-35
6AWG Battery Wire 10ft (bank to inverter) $15-20
Inline Fuse 30A between controller and batteries $10
Fuse/Breaker 100A between batteries and inverter $15-20
Battery Cables 4/0 AWG, 1ft jumpers for parallel $20-30
Extension Cord 12-gauge, 50ft (inverter to desk) $20-30
Kill-A-Watt Meter Verify clean AC output $25
Total $285-405

Wiring Diagram

                    ┌──────────────────────────────┐
                    │         SOLAR PANELS          │
                    │   ┌──────┐      ┌──────┐     │
                    │   │ 150W │──+──│ 150W │     │  String 1 (36V)
                    │   └──────┘  │   └──────┘     │
                    │             │                  │
                    │   ┌──────┐  │   ┌──────┐     │
                    │   │ 150W │──+──│ 150W │     │  String 2 (36V)
                    │   └──────┘      └──────┘     │
                    └──────────┬───────────────────┘
                               │ PV+ PV-
                               │ 10AWG
                    ┌──────────▼───────────────────┐
                    │      MPPT CONTROLLER          │
                    │      30A, 12V/24V              │
                    │  PV INPUT ──── BATTERY OUTPUT  │
                    └──────────┬───────────────────┘
                               │ BAT+ BAT-
                               │ 6AWG + 30A fuse
                    ┌──────────▼───────────────────┐
                    │       BATTERY BANK             │
                    │  ┌──────┐ ┌──────┐            │
                    │  │ 12V  │═│ 12V  │  (parallel)│
                    │  └──────┘ └──────┘            │
                    │  ┌──────┐ ┌──────┐            │
                    │  │ 12V  │═│ 12V  │  (parallel)│
                    │  └──────┘ └──────┘            │
                    └──────────┬───────────────────┘
                               │ 4/0 AWG + 100A breaker
                    ┌──────────▼───────────────────┐
                    │    1000W INVERTER              │
                    │  12V DC ──── 120V AC           │
                    └──────────┬───────────────────┘
                               │ 12-gauge extension
                    ┌──────────▼───────────────────┐
                    │     AC OUTLETS                 │
                    │  Desk │ Coffee Table │ Spare  │
                    └──────────────────────────────┘

Installation Checklist

Pre-Installation

  • Verify panel specs (Voc, Isc, Vmp, Imp) match wiring plan
  • Test each panel individually with multimeter (should read ~18V open circuit)
  • Verify battery bank voltage (12.4V+ for charged batteries)
  • Clear panel mounting area of snow/shade/debris

Wiring Order (safety: work from panels down)

  1. Mount panels or secure in optimal sun position (south-facing, 30-45° tilt)
  2. Connect panel strings in series (+ to -) with MC4 connectors
  3. Connect string outputs in parallel with Y-connectors (PV+ and PV-)
  4. Run 10AWG PV wire from panels to controller location
  5. Connect PV wires to MPPT controller PV input
  6. Connect battery bank to controller battery output (with 30A fuse)
  7. Connect inverter to battery bank (with 100A breaker)
  8. Run 12-gauge extension cord from inverter to desk zone

Battery Bank Wiring

  • Wire 4 batteries in parallel: all + together, all - together
  • Use 4/0 AWG cables for jumpers (short as possible)
  • Connect load/controller to diagonally opposite terminals (balances charge/discharge)
  • Torque all connections to spec

Testing

  • Verify controller shows PV input voltage (should be ~36V in sun)
  • Verify controller shows battery charging current
  • Verify inverter powers on without load
  • Test with single laptop first
  • Monitor for 1 hour: check for hot connections, smells, unusual sounds
  • Run Kill-A-Watt on inverter output to verify clean 120V AC
  • 48-hour stability test: leave system running under normal load

Documentation

  • Photo of wiring diagram on site
  • Photo of installed panels
  • Photo of battery bank and connections
  • Photo of controller display showing charge status
  • Upload all photos to issue #529

Safety Notes

  1. Always disconnect panels before working on wiring — panels produce voltage in any light
  2. Fuse everything — 30A between controller and batteries, 100A between batteries and inverter
  3. Vent batteries — if using lead-acid, ensure adequate ventilation for hydrogen gas
  4. Check polarity twice — reverse polarity WILL damage controller and inverter
  5. Secure all connections — loose connections cause arcing and fire
  6. Keep batteries off concrete — use plywood or plastic battery tray
  7. No Bitcoin miners on base load — explicitly out of scope

Estimated Runtime

With 600W panels and 400Ah battery bank at 50% DoD:

  • 200Ah × 12V = 2,400Wh usable
  • Laptop + monitor + accessories: ~100W
  • Runtime on batteries alone: ~24 hours
  • With daytime solar charging: essentially unlimited during sun hours
  • Cloudy days: expect 4-6 hours of reduced charging

Generated for issue #529 | LAB-004