Some checks failed
Smoke Test / smoke (pull_request) Failing after 20s
Complete deployment guide for 600W cabin solar array: - ASCII wiring diagram (panels → controller → batteries → inverter → AC) - Parts list with estimated costs ($285-405, under $500 budget) - 2S2P panel wiring configuration (36V to controller) - 4-battery parallel bank layout - Step-by-step installation checklist - Safety notes and estimated runtime Physical hardware task — documentation only. Closes #529.
7.5 KiB
7.5 KiB
LAB-004: 600W Solar Array Deployment Guide
Issue #529 | Cabin Compute Lab Power System Budget: $200-500
System Overview
4x 150W panels → MPPT controller → 12V battery bank → 1000W inverter → 120V AC
[PANELS 4x150W] ──series/parallel──► [MPPT 30A] ──► [BATTERY BANK 4x12V]
│
[1000W INVERTER]
│
[120V AC OUTLETS]
Wiring Configuration
Panels: 2S2P (two in series, two strings in parallel)
- Series pair: 18V + 18V = 36V at 8.3A
- Parallel strings: 36V at 16.6A total
- Total: ~600W at 36V DC
Battery bank: 4x 12V in parallel
- Voltage: 12V (stays 12V)
- Capacity: sum of all 4 batteries (e.g., 4x 100Ah = 400Ah)
- Usable: ~200Ah (50% depth of discharge for longevity)
Parts List
| Item | Spec | Est. Cost |
|---|---|---|
| MPPT Charge Controller | 30A minimum, 12V/24V, 100V input | $60-100 |
| Pure Sine Wave Inverter | 1000W continuous, 12V input | $80-120 |
| MC4 Connectors | 4 pairs (Y-connectors for parallel) | $15-20 |
| 10AWG PV Wire | 50ft (panels to controller) | $25-35 |
| 6AWG Battery Wire | 10ft (bank to inverter) | $15-20 |
| Inline Fuse | 30A between controller and batteries | $10 |
| Fuse/Breaker | 100A between batteries and inverter | $15-20 |
| Battery Cables | 4/0 AWG, 1ft jumpers for parallel | $20-30 |
| Extension Cord | 12-gauge, 50ft (inverter to desk) | $20-30 |
| Kill-A-Watt Meter | Verify clean AC output | $25 |
| Total | $285-405 |
Wiring Diagram
┌──────────────────────────────┐
│ SOLAR PANELS │
│ ┌──────┐ ┌──────┐ │
│ │ 150W │──+──│ 150W │ │ String 1 (36V)
│ └──────┘ │ └──────┘ │
│ │ │
│ ┌──────┐ │ ┌──────┐ │
│ │ 150W │──+──│ 150W │ │ String 2 (36V)
│ └──────┘ └──────┘ │
└──────────┬───────────────────┘
│ PV+ PV-
│ 10AWG
┌──────────▼───────────────────┐
│ MPPT CONTROLLER │
│ 30A, 12V/24V │
│ PV INPUT ──── BATTERY OUTPUT │
└──────────┬───────────────────┘
│ BAT+ BAT-
│ 6AWG + 30A fuse
┌──────────▼───────────────────┐
│ BATTERY BANK │
│ ┌──────┐ ┌──────┐ │
│ │ 12V │═│ 12V │ (parallel)│
│ └──────┘ └──────┘ │
│ ┌──────┐ ┌──────┐ │
│ │ 12V │═│ 12V │ (parallel)│
│ └──────┘ └──────┘ │
└──────────┬───────────────────┘
│ 4/0 AWG + 100A breaker
┌──────────▼───────────────────┐
│ 1000W INVERTER │
│ 12V DC ──── 120V AC │
└──────────┬───────────────────┘
│ 12-gauge extension
┌──────────▼───────────────────┐
│ AC OUTLETS │
│ Desk │ Coffee Table │ Spare │
└──────────────────────────────┘
Installation Checklist
Pre-Installation
- Verify panel specs (Voc, Isc, Vmp, Imp) match wiring plan
- Test each panel individually with multimeter (should read ~18V open circuit)
- Verify battery bank voltage (12.4V+ for charged batteries)
- Clear panel mounting area of snow/shade/debris
Wiring Order (safety: work from panels down)
- Mount panels or secure in optimal sun position (south-facing, 30-45° tilt)
- Connect panel strings in series (+ to -) with MC4 connectors
- Connect string outputs in parallel with Y-connectors (PV+ and PV-)
- Run 10AWG PV wire from panels to controller location
- Connect PV wires to MPPT controller PV input
- Connect battery bank to controller battery output (with 30A fuse)
- Connect inverter to battery bank (with 100A breaker)
- Run 12-gauge extension cord from inverter to desk zone
Battery Bank Wiring
- Wire 4 batteries in parallel: all + together, all - together
- Use 4/0 AWG cables for jumpers (short as possible)
- Connect load/controller to diagonally opposite terminals (balances charge/discharge)
- Torque all connections to spec
Testing
- Verify controller shows PV input voltage (should be ~36V in sun)
- Verify controller shows battery charging current
- Verify inverter powers on without load
- Test with single laptop first
- Monitor for 1 hour: check for hot connections, smells, unusual sounds
- Run Kill-A-Watt on inverter output to verify clean 120V AC
- 48-hour stability test: leave system running under normal load
Documentation
- Photo of wiring diagram on site
- Photo of installed panels
- Photo of battery bank and connections
- Photo of controller display showing charge status
- Upload all photos to issue #529
Safety Notes
- Always disconnect panels before working on wiring — panels produce voltage in any light
- Fuse everything — 30A between controller and batteries, 100A between batteries and inverter
- Vent batteries — if using lead-acid, ensure adequate ventilation for hydrogen gas
- Check polarity twice — reverse polarity WILL damage controller and inverter
- Secure all connections — loose connections cause arcing and fire
- Keep batteries off concrete — use plywood or plastic battery tray
- No Bitcoin miners on base load — explicitly out of scope
Estimated Runtime
With 600W panels and 400Ah battery bank at 50% DoD:
- 200Ah × 12V = 2,400Wh usable
- Laptop + monitor + accessories: ~100W
- Runtime on batteries alone: ~24 hours
- With daytime solar charging: essentially unlimited during sun hours
- Cloudy days: expect 4-6 hours of reduced charging
Generated for issue #529 | LAB-004